Status Of RMS and
Spot Billing
RMS Software
is developed by CBG
Present Status
•
Server room
for four City Divisions had setup with required Electrical and Civil work.
•
Servers of
four City Divisions and one O&M Dn is installed
at server room and required software loaded on these machines
•
Temporary LAN
was initially setup with 25 computers.
•
Data entry
started with engaging out-sourced agency.
•
Temporary LAN
extended to 35 computers to speed up data entry work.
•
Version 1.1.2
of RMS loaded on 7 servers and data entry for the balance consumers in progress
planned to be finished by 15th May 04
Progress of Data Entry
(
•
Data entry of
four City Divisions is done for
Ø 33/11 KV Transformers 68 Nos
Ø 11 KV Feeders 136 Nos
Ø 11 KV Poles 13313 Nos
Ø Distribution Transformers 3265 Nos
Ø L T Poles 46512 Nos
Ø Consumers 313361 Nos
•
100% Data entry up to consumer level is
completed on 30 Aug 03.
(O&M Division
•
Data entry of
O&M Division is done for
Ø 33/11 KV Transformers 50 Nos
Ø 11 KV Feeders 100 Nos
Ø 11 KV Poles 15189 Nos
Ø Distribution Transformers 2237 Nos
Ø L T Poles 42956 Nos
•
100% Data entry up to LT Poles level is
completed on 30 Aug 03.
(
•
Data entry of
Ø 33/11 KV Transformers 18 Nos
Ø 11 KV Feeders 47 Nos
Ø 11 KV Poles 4403 Nos
Ø Distribution Transformers 855 Nos
Ø L T Poles
21975 Nos
Ø Consumers 88175 Nos
•
100% Data entry up to Consumer level is
completed on 30 Aug 03.
(O&M Division
•
Data entry of
O&M Division
Ø 33/11 KV Transformers 28 Nos
Ø 11 KV Feeders 53 Nos
Ø 11 KV Poles 2020 Nos
Ø Distribution Transformers 2237 Nos
Ø L T Poles 42956 Nos
•
100% Data entry up to LT Poles level is completed
on 30 Aug 03.
Hardware
Required in RMS
(For Priority Divisions)
•
Hardware
Required in RMS for Priority Divisions( 4 City and 1 O&M Division of
|
Particulars |
Total Reqired |
Available |
Shortfall |
|
Servers |
10 |
10 |
0 |
|
PC P-IV |
234 |
172 |
62 |
|
DMPrinter(132C) |
101 |
41 |
60 |
|
DMPrinter (80C) |
62 |
28 |
34 |
•
Hardware
Required in RMS for Priority Divisions( City and O&M Divisions
|
Particulars |
Total Reqired |
Available |
Shortfall |
|
Servers |
4 |
4 |
0 |
|
PC P-IV |
79 |
42 |
37 |
|
DMPrinter(132C) |
30 |
15 |
15 |
|
DMPrinter (80C) |
21 |
11 |
10 |
Bottlenecks
•
Following
support were needed from CBG during data entry process
Ø Conversion of latest bill file data for city Circle
Ø Report generation of 11 KV and LT Poles for O&M
division.
Ø Modification permissions for O&M divisions.
Ø A provision for transferring last six readings of the
consumers from the existing LT Billing system as these readings are to be
displayed in the revised bill forms.
On Spot Billing
On spot billing will start with the rollout of RMS initially
in priority division and later on in other divisions as and when the RMS
billing is started which is being finalized by CBG form Jabalpur