| M.P.P.K.V.V.COMPANY LTD., | |||||||||
| WHERE EXTENSION WORK IS REQUIRED. | |||||||||
| May ,2008 | |||||||||
| Format B-1 - HT | |||||||||
| Sr. No. | Age wise Breakup | For want of forma- lities by consumer | For want of inspe- ction by licensee | For want of sanc-tion by Licensee | For want of issue of demand note by licensee | For want of install- ation of meter & release of connec-tion | Any Other Reason | ||
| On Part of Licensee | On Part of Consumer | ||||||||
| Indore Region | |||||||||
| 1 | Less than 1 Month | 10 | 0 | 4 | 0 | 0 | 0 | 0 | |
| 2 | 1 to 3 months | 24 | 0 | 0 | 0 | 0 | 0 | 3 | |
| 3 | 3 to 6 months | 16 | 0 | 2 | 0 | 0 | 0 | 1 | |
| 4 | More than 6 months | 13 | 0 | 0 | 0 | 0 | 0 | 5 | |
| Ujjain Region | |||||||||
| 1 | Less than 1 month | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
| 2 | 1 to 3 months | 6 | 0 | 3 | 0 | 0 | 0 | 0 | |
| 3 | 3 to 6 months | 0 | 0 | 1 | 0 | 0 | 0 | 5 | |
| 4 | More than 6 months | 0 | 0 | 0 | 0 | 0 | 2 | 8 | |
| Total West Zone Co. | |||||||||
| 1 | Less than 1 Month | 10 | 0 | 4 | 0 | 0 | 0 | 0 | |
| 2 | 1 to 3 months | 30 | 0 | 3 | 0 | 0 | 0 | 3 | |
| 3 | 3 to 6 months | 16 | 0 | 3 | 0 | 0 | 0 | 6 | |
| 4 | More than 6 months | 13 | 0 | 0 | 0 | 0 | 2 | 13 | |
| NO EXTENSION WORK IS REQUIRED. | |||||||||
| REASONS FOR PENDING | |||||||||
| Format B-2 - HT | |||||||||
| Sr. No. | Age wise Breakup | For want of forma- lities by consumer | For want of inspe- ction by licensee | For want of sanc-tion by Licensee | For want of issue of demand note by licensee | For want of install- ation of meter & release of connec-tion | Any Other Reason | ||
| On Part of Licensee | On Part of Consumer | ||||||||
| Indore Region | |||||||||
| 1 | Less than 1 Month | 0 | 0 | 1 | 0 | 0 | 0 | 0 | |
| 2 | 1 to 3 months | 1 | 0 | 0 | 0 | 0 | 0 | 0 | |
| 3 | 3 to 6 months | 1 | 0 | 0 | 0 | 0 | 0 | 0 | |
| 4 | More than 6 months | 1 | 0 | 0 | 0 | 0 | 0 | 0 | |
| Ujjain Region | |||||||||
| 1 | Less than 1 month | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
| 2 | 1 to 3 months | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
| 3 | 3 to 6 months | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
| 4 | More than 6 months | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
| Total West Zone Co. | |||||||||
| 1 | Less than 1 Month | 0 | 0 | 1 | 0 | 0 | 0 | 0 | |
| 2 | 1 to 3 months | 1 | 0 | 0 | 0 | 0 | 0 | 0 | |
| 3 | 3 to 6 months | 1 | 0 | 0 | 0 | 0 | 0 | 0 | |
| 4 | More than 6 months | 1 | 0 | 0 | 0 | 0 | 0 | 0 | |
| M.P.P.K.V.V.COMPANY LTD., | |||||||||
| WHERE EXTENSION WORK IS REQUIRED. | |||||||||
| REASONS FOR PENDING - Apr ,2008 | |||||||||
| Format B-1 - LT | |||||||||
| Sr. No. | Age wise Breakup | For want of forma- lities by consumer | For want of inspe- ction by licensee | For want of sanc-tion by Licensee | For want of issue of demand note by licensee | For want of install- ation of meter & release of connec-tion | Any Other Reason | ||
| On Part of Licensee | On Part of Consumer | ||||||||
| Indore Region | |||||||||
| 1 | Less than 1 Month | 4 | 0 | 2 | 0 | 0 | 0 | 0 | |
| 2 | 1 to 3 months | 6 | 0 | 2 | 0 | 0 | 0 | 34 | |
| 3 | 3 to 6 months | 6 | 0 | 0 | 0 | 0 | 0 | 2 | |
| 4 | More than 6 months | 6 | 0 | 0 | 0 | 0 | 0 | 20 | |
| Ujjain Region | |||||||||
| 1 | Less than 1 month | 7 | 0 | 0 | 0 | 0 | 0 | 13 | |
| 2 | 1 to 3 months | 0 | 0 | 0 | 0 | 0 | 0 | 19 | |
| 3 | 3 to 6 months | 0 | 0 | 0 | 0 | 0 | 0 | 15 | |
| 4 | More than 6 months | 0 | 0 | 0 | 0 | 0 | 0 | 31 | |
| Total West Zone Co. | |||||||||
| 1 | Less than 1 Month | 11 | 0 | 2 | 0 | 0 | 0 | 13 | |
| 2 | 1 to 3 months | 6 | 0 | 2 | 0 | 0 | 0 | 53 | |
| 3 | 3 to 6 months | 6 | 0 | 0 | 0 | 0 | 0 | 17 | |
| 4 | More than 6 months | 6 | 0 | 0 | 0 | 0 | 0 | 51 | |
| NO EXTENSION WORK IS REQUIRED. | |||||||||
| REASONS FOR PENDING | |||||||||
| Format B-2 - LT | |||||||||
| Sr. No. | Age wise Breakup | For want of forma- lities by consumer | For want of inspe- ction by licensee | For want of sanc-tion by Licensee | For want of issue of demand note by licensee | For want of install- ation of meter & release of connec-tion | Any Other Reason | ||
| On Part of Licensee | On Part of Consumer | ||||||||
| Indore Region | |||||||||
| 1 | Less than 1 Month | 281 | 28 | 9 | 0 | 138 | 0 | 26 | |
| 2 | 1 to 3 months | 9 | 0 | 1 | 0 | 1 | 0 | 0 | |
| 3 | 3 to 6 months | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
| 4 | More than 6 months | 1 | 0 | 0 | 0 | 0 | 0 | 0 | |
| Ujjain Region | |||||||||
| 1 | Less than 1 month | 130 | 0 | 0 | 0 | 0 | 0 | 25 | |
| 2 | 1 to 3 months | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
| 3 | 3 to 6 months | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
| 4 | More than 6 months | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
| Total West Zone Co. | |||||||||
| 1 | Less than 1 Month | 411 | 28 | 9 | 0 | 138 | 0 | 51 | |
| 2 | 1 to 3 months | 9 | 0 | 1 | 0 | 1 | 0 | 0 | |
| 3 | 3 to 6 months | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
| 4 | More than 6 months | 1 | 0 | 0 | 0 | 0 | 0 | 0 | |