| M.P.P.K.V.V.COMPANY LTD. | |||
| INDORE REGION | |||
| Sub :- | In the matter of perio dic certification of energy meters | ||
| DETAILS OF TESTING OF METERS THAT ARE CONTESTED BY CONSUMERS | |||
| AT DHAR LTMT LAB.CIRCLE-DHAR. | |||
| Sr.No. | Particulars | Electro-mechanical Meter | Electronic meters |
| 01] | No.of meters tested during | ||
| i] | FY - 2001-02 | 15 | 14 |
| ii] | FY-2002-03 | 6 | 114 |
| iii] | FY-2003-04 | 363 | 317 |
| iv] | FY-2004-05 | 10 | 564 |
| v] | FY-2005-06 | 1 | 451 |
| vi] | FY-2006-2007 upto April 2007 | ||
| Total : | 395 | 1460 | |
| 02] | No.of meters found defective | ||
| against above | |||
| i] | FY - 2001-02 | 3 | 1 |
| ii] | FY-2002-03 | 1 | 58 |
| iii] | FY-2003-04 | 230 | 195 |
| iv] | FY-2004-05 | 4 | 307 |
| v] | FY-2005-06 | 1 | 259 |
| vi] | FY-2006-2007 upto April'2007 | ||
| Total : | 239 | 820 | |
| 03] | Extent of defect out of total | ||
| defective meters | |||
| i] | No.of meters found slow from | 135 | 45 |
| 3% upoto 50% | |||
| ii] | No. of meters found slow above | 104 | 119 |
| 50% | |||
| iii] | No.of meters found fast by more | 0 | 77 |
| that 3% uypto 50% | |||
| iv] | No.of meters found fast by more | 0 | 133 |
| than 50% upto 100% | |||
| v] | No.of meters found fast more | 0 | 446 |
| than 100% | |||
| vi] | Other | 0 | 0 |
| Total :- | 239 | 820 | |
| Extent percentage of meter | |||
| running fastest out of [vi] | |||
| p/ws/Peti.146 | |||
| M.P.PASCHIM KSHETRA VIDYUT VITARAN CO.LTD.INDORE | |||
| INDORE REGION | |||
| Sub :- | In the matter of perio dic certification of energy meters | ||
| DETAILS OF TESTING OF METERS THAT ARE CONTESTED BY CONSUMERS | |||
| AT DHAR LTMT LAB.CIRCLE-DHAR. | |||
| Sr.No. | Particulars | Electro-mechanical | Electronic meters |
| meters | |||
| 01] | No.of meters tested during | ||
| i] | FY - 2001-02 | 15 | 14 |
| ii] | FY-2002-03 | 6 | 114 |
| iii] | FY-2003-04 | 363 | 317 |
| iv] | FY-2004-05 | 10 | 564 |
| v] | FY-2005-06 | 1 | 451 |
| vi] | FY-2006-2007 upto March''2007 | 2 | 528 |
| Total : | 397 | 1988 | |
| 02] | No.of meters found defective | ||
| against above | |||
| i] | FY - 2001-02 | 3 | 1 |
| ii] | FY-2002-03 | 1 | 58 |
| iii] | FY-2003-04 | 230 | 195 |
| iv] | FY-2004-05 | 4 | 307 |
| v] | FY-2005-06 | 1 | 259 |
| vi] | FY-2006-2007 upto March''2007 | 2 | 254 |
| Total : | 241 | 1074 | |
| 03] | Extent of defect out of total | ||
| defective meters | |||
| i] | No.of meters found slow from | 135 | 61 |
| 3% upoto 50% | |||
| ii] | No. of meters found slow above | 106 | 174 |
| 50% | |||
| iii] | No.of meters found fast by more | 0 | 102 |
| that 3% uypto 50% | |||
| iv] | No.of meters found fast by more | 0 | 169 |
| than 50% upto 100% | |||
| v] | No.of meters found fast more | 0 | 568 |
| than 100% | |||
| vi] | Other | 0 | 0 |
| Total :- | 241 | 1074 | |
| Extent percentage of meter | |||
| running fastest out of [vi] | 0 | HPL-3500% | |
| p/ws/Peti.146 | |||