| M.P.P.K.V.V.Co.Ltd., UJJAIN REGION | ||||||||||
| FORMAT D-1 | ||||||||||
| Status of pending application for New Connection as on 30 APR.'08 | ||||||||||
| Where Extension work required - H.T. | ||||||||||
| S. No. | Date of Application | Category | Reasons for pending | |||||||
| Ujjain Circle | ||||||||||
| 1 | 17.01.07 | The C.M.O.Nagarpalica Barnagar | Pumping station | Work to be completed by the applicant under 5% supervison charges | ||||||
| 2 | 17.01.07 | The C.M.O. Nagar Palika, Barnagar | Pumping station | Work to be completed by applicant. | ||||||
| 3 | 28.11.07 | M/s Dayaram Bhandargarh, Tarana | Cold Storage | Work to be completed by applicant. | ||||||
| 4 | 24.03.08 | M/s Super Formulations Pvt. Ltd., Ujjain | Pharmacutical Formulation | Work to be completed by applicant. | ||||||
| Dewas Circle | ||||||||||
| 5 | 01.08.07 | M/s M.S.K. Project India, Dewas | Hydral Project | Work to be completed by applicant. | ||||||
| 6 | 01.08.07 | M/s M.S.K. Project India, Dewas | Hydral Project | Work to be completed by applicant. | ||||||
| 7 | 01.08.07 | M/s M.S.K. Project India, Dewas | Hydral Project | Work to be completed by applicant. | ||||||
| 8 | 02.01.08 | Aameya Pacakging Pvt.Ltd., Dewas | Polythen Sheet & Bags | Work to be completed by applicant | ||||||
| 9 | 15.03.08 | M/s Khumani Steel, Dewas | Steel Rerolled | The consumer has not completed formalities. | ||||||
| 10 | 02.04.08 | M/s Mubarak Steel Pvt. Ltd., Dewas | Stee Rolling | The consumer has not completed formalities. | ||||||
| 11 | 21.09.07 | M/s Dev Kripa Steel Pvt. Ltd., Dewas | Mfg. of Steel | Work to be completed by applicant | ||||||
| 12 | 21.02.08 | M/s Irfan Shaikh, Dewas | Commercial Complex | Work to be completed by applicant | ||||||
| 13 | 04.03.08 | M/s Thakur Ramrati Shiksha Samittee, Vill. Rajpura, Dewas | College | The consumer has not completed formalities. | ||||||
| 14 | --- | M/s Shri Oil Industries, Loharda | Oil Mills | Under Sanction | ||||||
| 15 | --- | M/s CMO, W/W, Dewas | Water Works | Under Sanction | ||||||
| Shajapur Circle | ||||||||||
| 16 | 28.11.07 | M/s Neo Trades, Maxi | Tread Rubber | Work to be completed by applicant | ||||||
| 17 | 29.02.08 | The C.M.O., Nagar Panchyat, Maxi | Water Works | The consumer has not completed formalities. | ||||||
| 18 | --- | M/s Manorama Food Pvt. Ltd., Dewas | --- | Under Sanction | ||||||
| Ratlam Circle | ||||||||||
| 19 | 13.03.06 | M/s Indain Oil Corporation, Ratlam | Petrolium Department | 16 KM 33 KV line & 33 KV Bay work involved. The work will be completed by the M.P.P.K.V.V.Co.Ltd. | ||||||
| 20 | 20.12.06 | M/s Principal Jawahar Navoday Vidyalaya, Kalukheda, Ratlam | School/Hostel | Work to be completed by MPPKVVCo.Ltd. | ||||||
| 21 | 28.01.08 | The S.D.O., Water Resource Sub. Dn. Jaora, Man Kamneshwar | Lift Irrigation | Under Sanction | ||||||
| 22 | 28.01.08 | The S.D.O., Water Resource Sub. Dn. Jaora, Asawati | Lift Irrigation | The consumer has not completed formalities. | ||||||
| Mandsaur Circle | ||||||||||
| 23 | 17.01.08 | M/s Radhika Industries, Mandsaur | Oil Mills | Work to be completed by applicant | ||||||
| 24 | 25.01.08 | M/s Ambika Dehyadrates, Mandsaur | Garlic Industries | Work to be completed by applicant | ||||||
| Neemuch Circle | ||||||||||
| 25 | 01.09.07 | M/s Gomabai Neturlaya & Research Centre, Neemuch | Hospital & Reserch Centre | Work to be completed by applicant | ||||||
| 26 | 24.01.08 | M/s Shree Dhanuka Agro Pvt.Ltd. Neemuch | Oil Mills | Work to be completed by applicant | ||||||