| M.P.P.K.V.V.Co.Ltd., UJJAIN REGION | ||||||||||
| FORMAT D-1 | ||||||||||
| Status of pending application for New Connection as on 31 MAY'08 | ||||||||||
| Where Extension work required - H.T. | ||||||||||
| S. No. | Date of Application | Category | Reasons for pending | |||||||
| Ujjain Circle | ||||||||||
| 1 | 17.01.07 | The C.M.O.Nagarpalica Barnagar | Pumping station | Work to be completed by the applicant under 5% supervison charges | ||||||
| 2 | 17.01.07 | The C.M.O. Nagar Palika, Barnagar | Pumping station | Work to be completed by applicant. | ||||||
| 3 | 24.03.08 | M/s Super Formullation P.Ltd.Ujjain | Pharmacutical Formulation | Work to be completed by applicant. | ||||||
| 4 | 29.04.08 | M/s Shree Processors Ujjain | Expeller based Oil Mill | Under Sanction | ||||||
| Dewas Circle | ||||||||||
| 5 | 01.08.07 | M/s M.S.K. Project India, Dewas | Hydral Project | Work to be completed by applicant. | ||||||
| 6 | 01.08.07 | M/s M.S.K. Project India, Dewas | Hydral Project | Work to be completed by applicant. | ||||||
| 7 | 01.08.07 | M/s M.S.K. Project India, Dewas | Hydral Project | Work to be completed by applicant. | ||||||
| 8 | 15.03.08 | M/s Khumani Steel Dewas | Steel Rerolled | The consumer has not completed formalities. | ||||||
| 9 | 21.09.07 | M/s Dev Kripa Steel P.Ltd, Dewas | Mfg. of Steel | Work to be completed by applicant | ||||||
| 10 | 04.03.08 | M/s. Thakur Ramrati Shiksha Samittee Vill. Rajpura, Dewas | Collage | The consumer has not completed formalities. | ||||||
| 11 | _ | M/s Shree Oil Industries. Loharda | Oil Mills | Under Sanction | ||||||
| 12 | _ | M/s. CMO W/W Dewas | Water works | Under Sanction | ||||||
| Shajapur Circle | ||||||||||
| 13 | 28.11.08 | M/s Neo Trades, Maxi | Tread Rubber | Work to be completed by applicant | ||||||
| 14 | 29.02.08 | The CMO, Nagar Panchayat Maxi | Water works | The consumer has not completed formalities. | ||||||
| 15 | _ | M/s Manorama Foods P.Ltd. Shajapur | _ | Under Sanction | ||||||
| Ratlam Circle | ||||||||||
| 16 | 13.03.06 | M/s Indain Oil Corporation, Ratlam | Petrolium Department | 16 KM 33 KV line & 33 KV Bay work involved. The work will be completed by the M.P.P.K.V.V.Co.Ltd. | ||||||
| 17 | 20.12.06 | M/s Principal Jawahar Navoday Vidyalaya, Kalukheda, Ratlam | School/Hostel | Work to be completed by MPPKVVCo.Ltd. | ||||||
| 18 | 28.01.08 | The S.D.O., Water Resource Sub. Dn. Jaora, Man Kamneshwar | Lift Irrigation | Under Sanction | ||||||
| 19 | 28.01.08 | The S.D.O., Water Resource Sub. Dn. Jaora, Asawati | Lift Irrigation | Under Sanction | ||||||
| Mandsaur Circle | ||||||||||
| 20 | 25.01.08 | M/s Ambika Dehyadrates, Mandsaur | Garlic Industries | Work to be completed by applicant | ||||||
| Neemuch Circle | ||||||||||
| 21 | 01.09.07 | M/s Gomabai Neturlaya & Research Centre, Neemuch | Hospital & Reserch Centre | Work to be completed by applicant | ||||||
| 22 | 24.01.08 | M/s Shree Dhanuka Agro P.Ltd. Neemuch | Oil Mills | Work to be completed by applicant | ||||||
| 23 | _ | M/s Yash Enterprises Neemuch | Stone Crushing | The consumer has not completed formalities. | ||||||
| 24 | _ | M/s Gopawat Enterprises Neemuch | Stone Crushing | The consumer has not completed formalities. | ||||||
| 25 | _ | M/s Chetal Enterprises Neemuch | Stone Crushing | The consumer has not completed formalities. | ||||||
| 26 | 24.01.08 | M/s Shree Dhanuka Agro Pvt.Ltd. Neemuch | Oil Mills | Work to be completed by applicant | ||||||