| M.P.P.K.V.V.COMPANY LTD. | ||||
| INDORE REGION | ||||
| STATUS OF PENDING APPLICATIONS FOR NEW CONNECTIONs. | ||||
| AS ON 30.04.2008 | ||||
| [Where extension work] | ||||
| [High Tension] | ||||
| Sr. No. | Date of Application | Name / Address of Applicant | Category | Reasons for pending. |
| CITY CIRCLE, INDORE | ||||
| 1 | 08.11.07 | M/s Apna Palace Hotel | Hotel | Pending for Line Extension work. |
| Dhar Road, Indore | the formalities. | |||
| 2 | 28.11.07 | The President | School | Pending for Line Extension work. |
| Digamber Jain School, Indore | ||||
| 3 | 28.11.07 | M/s Ashoka Buildcom | Bitchin Plant | Pending for Line Extension work. |
| Ring Road, Musakhedi | ||||
| 4 | 06.12.07 | M/s. Gurunanak Industries | PVC Pipe | Pending for Line Extension work. |
| Sanwer Road, Indore | ||||
| 5 | 06.12.07 | M/s. Tarmal Industries | Rolling Mill | Pending for Line Extension work. |
| Sanwer Road, Indore | ||||
| 6 | 19.12.07 | M/s. Neeraj Pratibha | Mixing plant | Pending for Line Extension work. |
| AB Road, Indore | ||||
| 7 | 29.12.07 | M/s. SDO Residency Kothi | Residency | Consumer has not completed |
| Residency, Indore | the formalities. | |||
| 8 | 01.01.08 | M/s Narayan Rubber Industries | PVC Pipe | Pending for Line Extension work. |
| Sanwer Road, Indore | ||||
| 9 | 30.01.08 | M/s Salimar Palm Energy | Housing Soc. | Sanction is awaited. |
| Users Samiti, Pipaliyahana | ||||
| 10 | 09.02.08 | The Asstt.Engg.M/s AKVN, | Office Use | Consumer has not completed |
| Indore | the formalities | |||
| 11 | 12.02.08 | M/s Scientech Technology | Component | Pending for Line Extension work. |
| Indore | ||||
| 12 | 26.02.08 | M/s Javeri Textiles | Rubber Co. | Pending for Line Extension work. |
| Indore | ||||
| 13 | 26.02.08 | M/s Universal Flexipack | Flexipack | Sanction is awaited |
| Scheme No.71, Indore | ||||
| 14 | 14.03.08 | M/s Suyash Industries | PVC | Pending for Line Extension work. |
| Pipaliyarao, Indore | ||||
| 15 | 14.03.08 | M/s Smooth Developers | Hotel | Pending for Line Extension work. |
| Scheme No.54,Indore | ||||
| 16 | 21.04.08 | M/s Shri Elastic Pvt.Ltd., | Elastic | Pending for Line Extension work. |
| Sanwer Road, Indore | ||||
| O&M CIRCLE, INDORE | ||||
| 1 | 30.11.06 | M/s Kothari Finolex | H.T.Conn. | Consumer has not completed |
| Pithampur | formalities. | |||
| 2 | 27.04.07 | M/s Ranbaxy Laboratories, | H.T.Conn | Consumer has not completed |
| Indore | formalities. | |||
| 3 | 22.06.07 | M/s. C.M.Corporation | HT Conn. | Consumer has not completed |
| Hatod, Depalpur | formalities. | |||
| 4 | 30.06.07 | M/s. Ruchi Soya Industries | HT Conn. | Consumer has not completed |
| Indore | formalities. | |||
| 5 | 09.07.07 | Jila Sanyojak Adim Jati | HT Conn. | Work under progress |
| Indore | ||||
| 6 | 19.07.07 | M/s Indes Medical College | HT Conn. | Work under Progress |
| Indore | ||||
| 7 | 27.09.07 | M/s ACE Engineering | H.T.Conn. | Consumer has not completed |
| Indore | formalities. | |||
| 8 | 30.08.07 | M/s RDC Concrete,Indore | H.T.Conn. | Consumer has not completed |
| formalities. | ||||
| 9 | 24.09.07 | M/s Satayam Cotton | H.T.Conn. | Work under progress |
| Mhow | ||||
| 10 | 01.11.07 | M/s Digital Micro Roto | H.T.Conn. | Work under progress |
| Pithampur | ||||
| 11 | 01.11.07 | M/s Krishna Sprining | H.T.Conn. | Work under progress |
| Pithampur | ||||
| 12 | 01.11.07 | M/s Pick N Pouch | H.T.Conn. | Consumer has not completed |
| Pithampur | formalities. | |||
| 13 | 13.12.07 | M/s. Sahara India | H.T.Conn. | Consumer has not completed |
| Indore | formalities. | |||
| 14 | 13.12.07 | M/s. Sahara India | H.T.Conn. | Consumer has not completed |
| Indore | formalities. | |||
| 15 | 16.01.08 | M/s Ganpati Industries | H.T.Conn | Consumer has not completed |
| Depalpur | formalities. | |||
| 16 | 16.01.08 | M/s Champion Components | H.T.Conn | Consumer has not completed |
| Pithampur | formalities. | |||
| 17 | 01.01.08 | Smt. Shashi Bala Agarwal | H.T.Conn | Consumer has not completed |
| Indore. | formalities. | |||
| 18 | 29.02.08 | M/s Parth Polipack | H.T.Conn | Consumer has not completed |
| Pithampur | formalities. | |||
| 19 | 22.02.08 | M/s Navbharat Polimers | H.T.Conn | Consumer has not completed |
| Pithampur | formalities. | |||
| 20 | 25.02.08 | M/s Gopal Enterprises | H.T.Conn | Consumer has not completed |
| Indore | formalities. | |||
| 21 | 29.02.08 | M/s Dilip Agarwal | H.T.Conn | Consumer has not completed |
| Indore | formalities. | |||
| 22 | 01.02.08 | M/s Jaideep Glass Works | H.T.Conn | Consumer has not completed |
| Pithampsur | formalities. | |||
| 23 | 01.08.07 | M/s Indotech Machine | H.T.Conn | Consumer has not completed |
| Indore | formalities. | |||
| 24 | 11.02.08 | M/s Shreepati Pharmacecuticals | H.T.Conn | Consumer has not completed |
| Pithampur | formalities. | |||
| 25 | 30.12.07 | M/s Jagran Social Welfare | H.T.Conn | Consumer has not completed |
| Indore | formalities. | |||
| 26 | 29.03.08 | M/s Ganpati Metal | H.T.Conn. | Under Sanction |
| Depalpur | ||||
| 27 | 28.03.08 | M/s Choithram Cheritable | H.T.Conn. | Under Sanction |
| Depalpur | ||||
| 28 | 05.03.08 | M/s Jepika Paints | H.T.Conn | Consumer has not completed |
| Indore | formalities. | |||
| 29 | 09.03.08 | M/s Masand Agreetech | H.T.Conn | Consumer has not completed |
| Indore | formalities. | |||
| 30 | 12.09.07 | M/s Metrolls Pvt.Ltd., | H.T.Conn | Consumer has not completed |
| Indore | formalities. | |||
| 31 | 26.10.07 | M/s Cap & Seal, | H.T.Conn | Consumer has not completed |
| Pithampur | formalities. | |||
| 32 | 10.04.08 | M/s Kanha Aluminium | H.T.Conn | Under Sanction |
| Pithampur | ||||
| 33 | 23.04.08 | M/s Gaurang Metal | H.T.Conn | Under Sanction |
| Indore | ||||
| 34 | 17.04.08 | M/s Som Project Pvt.Ltd., | H.T.Conn | Under Sanction |
| Pithampur | ||||
| 35 | 19.04.08 | M/s Rashtriya Jansahayog Bal Vikas | H.T.Conn | Consumer has not completed |
| Depalpur | formalities. | |||
| 36 | 29.03.08 | M/s Vindals Chemical, | H.T.Conn | Consumer has not completed |
| Pithampur | formalities. | |||
| 37 | 29.03.08 | M/s Torino Lab. | H.T.Conn | Consumer has not completed |
| Pithampur | formalities. | |||
| O&M CIRCLE, BARWANI | ||||
| 1 | April,08 | M/s Advantage & Equa Fund P.Ltd. | H.T. | Formalities Not completed |
| Jamli - Barwani | ||||
| O&M CIRCLE, KHANDWA | ||||
| 1 | 18.06.07 | M/s Rakesh Bansal | Stone | Want of Charging Report. |
| Bhawsinghpura | ||||
| 2 | 18.06.07 | M/s Nagin Bansal, | Crusher | Want of Charging Report. |
| Bhawsinghpura | ||||
| 3 | 09.08.07 | A.,E., PHE, Tapti River,Burhanpur | Siverage & Pumping. | Pending for Extension works. |
| 4 | 31.10.07 | M/s Ajmani Agro Industries | Ginning & Oil | Pending for Extension works. |
| Pandhana Road, Khandwa | Mills | |||
| 5 | 01.11.07 | The Manager, | L&Water Pump. | Want of ME. |
| Dawat Trust Dargah-E-Hakimi, | ||||
| Burhanpur | ||||
| 6 | 31.01.08 | M/s Abhishek Cinema | Formalities not completed. | |
| Khandwa | ||||
| 7 | 31.01.08 | M/s Omprakash Champalal | Dal & Oil Mill. | For Want of Sanction. |
| Moghat Road, Khandwa | ||||
| 8 | 07.03.08 | M/s Amity Polymers Pvt.Ltd | IP | Formalities Not completed |
| Indore Road, Khandwa | ||||
| 9 | 11.02.08 | M/s Kamal Processors Pvt.Ltd | Cloth Process. | For want of sanction. |
| Alamganj, Burhanpur | ||||
| 10 | 25.02.08 | M/s Kamal Cot.Spin Pvt.Ltd., | Spinning Mill | Formalities Not completed |
| Khandwa Road, Burhanpur | ||||
| 11 | 14.03.08 | M/s Balaji Udhyog Pvt.Ltd., | Cloth Process. | For want of sanction. |
| Alamganj,Burhanpur | ||||
| O&M CIRCLE, DHAR | ||||
| 1 | 11.10.06 | Power Grid Corporation | H.T.Conn. | Formalities not completed. |
| villagfe- Apodiya, the. Sardarpur | ||||
| 2 | 29.08.07 | M/s Mahima Fibres Pvt.Ltd.Bakaner | H.T. Conn. | Sanction awaited. |
| 3 | 24.04.08 | M/s Platinum Cements Pvt.L:td | H.T.Conn. | For Want of Survey |
| Tirla | ||||
| 4 | 09.04.08 | M/s Gurukripa Associates | H.T.Conn. | For Want of Survey |
| Dhar | ||||
| STATUS OF PENDING APPLICATIONS FOR NEW CONNECTIONs. | ||||
| AS ON 30.04.2008 | ||||
| [No extension work] | ||||
| [High Tension] | ||||
| CITY CIRCLE, INDORE | ||||
| 1 | 11.10.07 | M/s Kanchan Cousine, | Hotel | Consumer has not completed |
| Tukoganj, Indore. | formalities | |||
| 2 | 26.10.07 | M/s Indore Rolling Mills, | Rolling Mills | Consumer has not completed |
| Shivaji Nagar, Indore | formalities | |||
| 3 | 19.03.08 | M/s Rahil Enterprises, | Office | For want of formalities. |
| Scheme No.54,Indore | ||||